November 2025
Building A is approaching the fifth floor, with two more to go before topping off by the end of January. Private pool forms are being poured, and the foundation work for the underground parking, pavilion, and 50-metre swimming pool is well underway.
October 2025
Basement complete and vertical construction underway on ground and second floors as Sudara enters final quarter. Bangkok Post reports bumper property year as high season approaches. Discover why visible construction momentum matters for investors.
September 2025
Foundation work completes with critical slab installations and column reinforcement as Sudara prepares for vertical construction. CBRE Thailand identifies Phuket as Southeast Asia's most dynamic residential market, validating investment fundamentals.
August 2025
Foundation work advances with basement flooring, concrete footings, and rebar installation marking progress toward vertical construction. Plus: The Nation Thailand reports Phuket property market value soars past 45 billion THB as global developers recognize investment potential.
July 2025
Excavation complete and foundation setting underway as Sudara transitions to vertical construction phase. Concrete operations active across all building zones. Discover why this milestone matters for investors evaluating Phuket's luxury market.
June 2025
Basement excavations begin and infrastructure advances as Sudara's summer construction momentum builds. Plus: The Thaiger identifies Bangtao as Phuket's go-to neighborhood for expats and investors, validating our location strategy.
May 2025
Piling complete and main construction begins with Vasi Company, the builder behind Andara Villas, Amanpuri, and Twin Palms. Plus: Robb Report and Bangkok Post coverage highlights Sudara's positioning in Phuket's surging luxury market.
March 2025
Over 1,800 foundation piles installed as Sudara's physical form emerges across all development zones. Discover how Allan Zeman's proven track record in luxury development is taking shape in Phuket's most exclusive low-density condominium community.
February 2025
Piling work surges from 10% to 45% in one month as Sudara's foundation takes shape. Plus: Phuket tourism hits 8.66M arrivals in 2024, strengthening the investment case for owners. Discover Phuket's most exclusive low-density development.
January 2025
Just two months into construction, Sudara's foundation work has reached 10% completion. Discover how Phuket's lowest-density luxury development is transforming from vision to reality, backed by the developer behind Hong Kong's Lan Kwai Fong and Andara Resort. Your exclusive opportunity awaits.